When doing the confirmations the standard setup for the actual hours is 0.000 (3 zeros after the comma) but now I have a problem when doing the confirmations on a specific Order type (PM06) it uses 0.0 (1 zero after the comma)
This causes a problem when I add up the column it gives me 2 separate totals.
Can anyone help me to rectify this problem.
Hi,
For the quantity of work the assigned domain (ARBEIT) is limited to one decimal place. So regardless of the Unit of Measure definition this field can only accept a single decimal. If you need to enter more precise values the option would be to enter a unit of minutes (rather than hours).
-Paul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi Andrew,
It looks as though I have been able to simulate what you have - see screenshot below.
Using a 'H' instead of 'HR' allows two decimal points in IW41 for the 'Actual Work' field, with a mixture of both 'H' and 'HR' as UOM's for different operations in an order the Actual Work final value ends up as a 3 decimal point number.
Can you check the UOM for all your Order Types on the Operations tab?
It's possible that you may have a different UOM set in the Task Lists from what's been configured as default values for units of operation in OIO9.
Regards,
Khayyam
Hi,
Check the settings in CUNI for HR and H. Here the number of decimal places can be specified.
However, you will still be limited to entering confirmations with maximum of 2 decimal places. This is because field Actual Work (AFRUD-ISMNW_2) uses data element ISMNW_2 which is limited to 2 decimal places.
-Paul
Hi Paul
Your advice worked, thanks, the settings for the decimal points are now correct.
I now have a problem with one of the Order types using the HR setting for actual work and the rest using H as you can see on the image below. Is there somewhere in config that this can changed/corrected?
Thanks
Andrew
Hi,
The UoM default for operations can be defined based on Planning Plant. The customizing path is as follows:
Plant Maintenance and Customer Service > Maintenance and Service Processing > Maintenance and Service Orders > General Data > Define Default Values for Units for Operation
This is the value that will default for new operations as they are created.
-Paul.
Hi,
The default is effective when the operation is first created. It is a default so can be overwritten by the user. Is it possible that this order type is being created in some particular way - maybe via BAPI or operations are created from a task list? Is the default 'wrong' when you create this order type manually from IW31?
There is a UoM entry at customizing point -
Functions and Settings for Order Types > Default Values for Task List Data and Profile Assignments
I don't see this affecting the normal manual input of operations via IW31.
-Paul
hey Andrew,
Glad you got it sorted. As we have mentioned above, you also need to check the Task Lists. If your Task List operations still contain 'H' as UoM then all orders where those task lists are used will use 'H' as the UoM.
To check the orders where you have a different UOM, try this:
Cheers,
Khayyam
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.