SAP Solution Manager
Value Management Dashboard - Formulas of graphs in 'Quick View'
Tags:
Graph 1: Achievement History
Deviation from Target value in percent
Formula:
(Baseline – Kpi value) / ( Baseline – Target value) *100
Graph 2: Plan/Actual History
Deviation of KPI value to Set Value in %
Formula:
((KPI value / Set value)*100) - 100
Graph 3: KPI Value History
Measurement points (= Measurement line) in comparision to Baseline (= starting date / starting value), Target (=Target value / target date) and Set value
Formula: -
Graph 4: Monthly Improvement History
Current value in comparison to previous value (increase or descrease)
Formula:
(( KPI value current * 100 ) / KPI value previous ) -100