Below are few important steps of the process with [Timelines]:

0. End-to-End Procedure Overview [0.07 – 0.23]                                  

1. Homogenous System Copy [0.25 – 5.35 ]: Using the System Copy option in SWPM, the copy of  BW7.00 on MaxDB (Dual stack) is created. [VA2 is the source and the copied system is KA5]


> [0.38 – 2.25]:  Source System Export

> [2.32 – 4.52] : Target System Installation

> [5.00 – 5.35] : Post Copy Steps

2. Dual-Stack Split [ 5.40 – 8.22] : Using the Dual Stack Split (DSS) Option in SWPM, the Copied system is split. [KA5 is now ABAP only, JA6 is a separate JAVA System]


3. Database Migration Option (DMO) for BW on SAP HANA[8.25 - 20.23]:

Only the BW ABAP stack (KA5) is considered for the Migration to SAP HANA using the DMO in SUM.  Refer to SAP Note 1813548 - Database Migration Option (DMO) for Software Update Manager

> 8.50 : BW Migration Cockpit (Report - ZBW_HANA_MIGRATION_COCKPIT)

Tool

SAP Note

ZBW_HANA_MIGRATION_COCKPIT

SAP Note 1909597

ZBW_HANA_CHECKLIST

SAP Note 1729988

ZBW_ABAP_ANALYZER

SAP Note 1847431

ZBW_TRANSFORM_FINDER

SAP Note 1908367

/SDF/HANA_BW_SIZING

SAP Note 1736976


> 8.55 : BW Housekeeping , BW Pre/Post Upgrade Tasklists (Transaction - STC01) ; SAP Note 1829728, 1734333

> 9.05 : Installation of SAP HANA (SP08) using hdblcm(gui)


  Start of DMO

> 10.05 : Configuring the SAP Host Agent to SUM (SP10)

> 10.16 : Execution of DMO in the browser (SAP UI5)

> 10.25 : Generation of stack.xml in Solution Manager

> 10.30 : [0.0%] Provide stack.xml

> 10.50 : [0.8%] Update SPAM to the latest version available

> 11.30 : [1.9%] Provide the Migration Key [ http://service.sap.com/migrationkey]

> 12.32 : [6.8%] DMO Tool Configuration

> 12.50 : [7.5%] Provide details of SAP HANA database Installed

> 15.00 : [15.6%] End of Extraction Phase

> 15.45 : [21.3%] ASU Toolbox (/ASU/UPGRADE), SAP Note 1000009

> 15.50 : [21.3%] End of Checks Phase

> 16.05 : [23.9%] Lock Development Environment

> 16.30 : [41.3%] Repository Modifications

> 17.13 : [65.0%] Preparations of Downtime

> 17.25 : [66.0%] Backup Request and Verify Database Backup

> 17.45 : [66.1%] End of Preprocessing Phase

> 18.30 : [89.9%] End of Downtime

> 18.35 : [90.6%] End of Execution Phase

> 20.04 : [100%] Migration Completed

More Information:

For the detailed Steps of the DMO process, please refer - SAP First Guidance - Using the DMO Option to Migrate BW on HANA