on 08-10-2008 12:34 PM
hi
gurus
what is teco
TECO -Means Technical Completed Used In Process /Production Orders.
Its is STATUS of The Order.An Order can Be deleted only
TECO Status.
Regards
Siddarth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pankaj,
Technical completion means ending a production order from a logistical viewpoint. This function is usually used, if the execution of an order has to be stopped prematurely or if the order could not be executed in the required manner and open requirements for the order (reservations, capacities) should be deleted.
The following actions are executed if an order is set to Technically complete.
The order is not relevant for MRP planning
Reservations are deleted
Capacity requirements are deleted
Purchase requisitions for external operations or non-stock materials are deleted
The order and its operations receive the system status Technically Completed (TECO)
If an order is technically complete, you cannot change it. The fields in the order are displayed but cannot be changed. You can however cancel technical completion, for instance if order data has to be changed.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Pankaj,
1.TECO stands for Technically Completed Status of a production order.
2.It's given to those production orders which are to be stopped prematurely due to some reason,say
mistakenly you have created a production order for X instead of Y.So you have to delete the open
reservations,capacities meant for that order.
3.One more thing before closing a production order,that particualr production order must be having either
TECO status or Released.
4.To perform this function goto change mode of production order CO02 ,top menu Functions---> Restrict
processing -
> Technically complete.
5.After technical completion you can still make postings for the order. For instance, material withdrawal or
a confirmation can be posted if they were previously forgotten.Eg Say we have set the TECO status for a
production order,but still Using T code CO11N we can do confirmation.
6.[Link for SAP help regarding TECO|http://help.sap.com/saphelp_erp60_sp/helpdata/en/a5/63198843a211d189410000e829fbbd/frameset.htm]
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
TECO - Means Technical Completion of the Production/Process order.
Technical completion means ending a production order from a logistical viewpoint. This function is usually used, if the execution of an order has to be stopped prematurely or if the order could not be executed in the required manner and open requirements for the order (reservations, capacities) should be deleted.
The following actions are executed if an order is set to Technically complete.
The order is not relevant for MRP planning
Reservations are deleted
Capacity requirements are deleted
Purchase requisitions for external operations or non-stock materials are deleted
The order and its operations receive the system status Technically Completed (TECO)
Regards,
Siva
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.