Planed costs on Simulation Version

Former Member
0 Kudos

Where can I see the planed costs on Simulation?

I have an escenario where the project is created as Simulation, and after this one is evaluated on duration and costs, the user transfer the simulation to an operative project, but I need to see the planed costs.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Thank's for the data, But I been doing a research about how the data is stored on SAP tables, your answer was very helpfull because now I know how to verify if the data I'm seen on the tables are correct.

Former Member
0 Kudos

Hi ,

Go to trnsaction CNS41 Structure Overview report

Press The Push button DB Profile

Tick on Version data in Origin

here u can select the simulation versions for which u want to see the Project info with differentiated colors

by selection of Project planned cost field