on 08-09-2008 1:21 AM
Where can I see the planed costs on Simulation?
I have an escenario where the project is created as Simulation, and after this one is evaluated on duration and costs, the user transfer the simulation to an operative project, but I need to see the planed costs.
Thank's for the data, But I been doing a research about how the data is stored on SAP tables, your answer was very helpfull because now I know how to verify if the data I'm seen on the tables are correct.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
Go to trnsaction CNS41 Structure Overview report
Press The Push button DB Profile
Tick on Version data in Origin
here u can select the simulation versions for which u want to see the Project info with differentiated colors
by selection of Project planned cost field
Rgds
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.