on 08-08-2008 5:05 PM
i wants to change the quantity in billing doc after pgi
plz
give me the ans
Its not possible,
may i know the reason why you want to change the quantity after done the billing.
If u wan to cahnge the quantity, u need to cancel the billing and reverse the pgi , then change te quantity in delivery
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
no action since over two months, I close this thread
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Maha Lingam
No u can not change qty. in billing once PGI is done. If u want to change the qty then U have to reverse the PGI Tcode VL09 and after that u can change qty in Delivery Tcode VL02N and again u have to do PGI.
Thx.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear maha
It is not possible to change the quantity once PGI is done. The only option is to cancel via VL09
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.