Dear all
Please explain me the integeration of PM/EHS with reference to Work Permit Process. Is there any notification for closing or approving by EHS in SAP. Is there any role for SAP EHS in work permit process.
Thanks.
Vikram Sethi
Hi Vikram,
I don not know about work permit process but regarding the PM and EHS integration I know little.
In EHS -> Risk Assessment and or Incident Accident log -> Technical Safety measures -> For any outstanding task we can create notification that will go to PM.
Notification type is OS.
Regards,
Smita
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Vikram,
There is a permit documentation under
http://help.sap.com/erp2005_ehp_03/helpdata/EN/01/d54a354ab311d189740000e8322d00/frameset.htm
Further exteneded version for permit is WCM (Work Clerance Management) for simple & exteneded versions.
http://help.sap.com/erp2005_ehp_03/helpdata/EN/2b/1b713896fab752e10000009b38f889/content.htm
Ramesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.