Hi,
I need to do Earned Value Anlysis for a project using Statistical Key figures. I have created SKF and SKF groups and assigned it to the value categories. After that, to run Progress Analysis Workbench (T.COde - CNPAWB), what I have to do? What are the customizing I have to do?
Kindly tell me the process/procedure for the same.
Regards
Prabu
Dear prabhu
the followig are the steps
1) define the quantitiy proportionality method in IMG
2) do all basic progess configurations.
3) assign the quant propo method & POC weightage to the lowest object in the project structure
4) Plan the SKF for that object in respective T.Code for the respective period
5) run CNE1 for that period
6) see the CNE5 report.
Regards
Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.