Project triggerd from Sales order

Former Member
0 Kudos

Hi,

In assembly processing we trigger the Project from sales order by assigning the std template to the Sales material.But if I use the same material for Quotation/contract the std project get triggered I want the Project shuld triggered thru sales order only not thru any other doc. How to schieve this ?

Rgds

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Have a different item category be determiined on those document types. Assembly processing utilizes item category on sales document line items as one piece of getting the whole thing to work.

Mike