on 08-07-2008 5:49 AM
Hi,
we facing the issue of whenever planned order generated after optimizer run. if the quantity of planned order < 1 i.e 0.8pcs . It will get stuck and won't cif to R3... any solution for this ..??
thx in advanced
regards
Hi
Can you please clarify the following:
1. Your Base Unit of Measure.
2. Any Min/Max Lot and rounding values maintained in ECC/APO.
3. PPM/Prod Version Lot sizes defined.
4. What is your BOM base quantity?
Also please elaborate the issue with proper examples, for us to help you better.
Regards,
Manjit
Edited by: Manjit Pahal on Aug 7, 2008 2:00 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Did not get your requirement
What is your BUM and what is your demand, Is your demand qty is in decimals
Pls let us know, so that it will be clear
regards
Vijay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.