Hi,

How to use network activities to book hours and what are the possibel ways?

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

thanks

Former Member
0 Kudos

Hi,

One needs to created work centers and activity types for this.

Planning of activity types and then posting against this activity will post hours against the network.

If you are assigning resources also, then hours entry in CATS will post hours against activity.

regards

Pratap.V

Former Member
0 Kudos

The work carried out for a netwrok activity is captured in SAP using confirmations. where in u the time/hours spent for the activity are captured. The following link provides u the full details about the same.

http://help.sap.com/saphelp_erp60_sp/helpdata/en/8e/b9853488601e33e10000009b38f83b/frameset.htm

CATS is very important in this regard.

Regards