At where could the PR be created by defined item categories...??

Former Member
0 Kudos

Hi,

How to config could let the PR auto generated for specific item categories???

I checked item categories definiation in SPRO, but didnt find corresponding checkbox kinds of....

Thank you very much!!

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

u cannot configure automatic PR through item categories, instead u can configure the same through Schedule lines.use VOV6.go to the details of ur schedule line, assign purchase order document type NB and maintain item category as 0005. then , PR can be created automatically..

hope it helps..

regards..

yogi...

Former Member
0 Kudos

Hi,

Thanks for the reply.

Why the PR related to schedule line?

What kind of business scenario behind them???

Thank you.

Former Member
0 Kudos

Hi,

let me explain in simple terms..Schedule line contains delivery relevent data like Delivery dates,etc..

suppose customer ordered 100 items.we have 60 only.then Pr should be raised for remaining 40.that means we have to confirm that when we r planning to make the material available for DELIVERY..so, obviously PR is relevent for Schedule lines..

hope it clarifies ur doubt..

regards..

yogi...

Answers (3)

Answers (3)

Former Member
0 Kudos

hi

pls refer the follow link for third party order

http://help.sap.com/saphelp_46c/helpdata/en/e6/4a78e39e0311d189b70000e829fbbd/content.htm

reg

Deepak

Former Member
0 Kudos

Hello Hoo Laa,

in VOV7, check the item category TAS/TAB and in the tab 'Transaction Flow' U'll find a checkbox 'Create PO Automatic'. If you need your own, copy the above item category. Now, apart from this you'll have to mention the default PO Doc type in the Schedule Line category definition in VOV6.

It is available at Schedule line(also) since they are the once which indicate the confirmation of the quantity.

Rgds,

Rags.

Former Member
0 Kudos

Self answer:

Item categories doest control PR directly...but there is an schedule line details put CS and you could find the auto PR generations checkbox.

For some 3rd party process...