Planning Actual Monthly for activity input

Former Member
0 Kudos

Hi All,

can we make planning or actual by monthly using activity input? Should i use tcode CJ40 or CJR2 ? Please guide me in detail .

Cheers,

Nies

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

In CJR2, slect the cost element line item and click the first icon in the above toolbar for planning period-wise.

If you want to do for activity type, go to KP26.

Hope this is what you wanted.

regards

Pratap.V

Former Member
0 Kudos

Hi Pratap,

I already choose CJR2 ...put WBS and CE ...i put in August...when i save it ...why the system distribute to other months and the distribution key default to 2...even in SPRO i create new profile and change the distribution key to 0...it always default to 2...

I would like to do only for August..dont want to distribute to other months...

what should i do?