We have a requirement that the billing due list should only pick the items for billing if all the items for that order are delivery completed.
So basically it has to wait till the last item on the order is shipped before it can generate the billing document for any item for that order. Any suggestions how can we archive this?
Thanks.
Achilles
Hi
This is not possible. One alternative is not to allow delivery split. If you create 'Delivery Group' for all the line items in the sales order - then the schedule lines for all the items will confirm the delivery dates on which all the items will be available for delivery though certain items are available even before that date. This way you can do delivery for all the items in a single delivery and can achieve your requirement. This may not perfectly meet your requirement since the delivery of certain line items is getting delayed. This is only an alternative.
Thanks,
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
no action since over two months, I close this thread
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.