on 08-05-2008 1:31 PM
I am trying to create order from APO DS Dash board (/SAPAPO/CDPS0).
Got an errror
> Order could not be scheduled.
> Error occured while creating an order.
I check all relevant master data (PPM, Product, location etc..)
Everything is fine..
Even resource is avaiable.
I am facing these problems for many products.
Could any one help me?
Thanks,
Vipul Shah
Hello ,
In the DS board the order creation and scheduling will be influenced by the 'DS strategy profile'. Check the settings of the DS strategy profile you are using .
Try to create the orders by setting the "Sched.Mode" in the profile to 'ifinite scheduling'.
Also check settings in the tab ' Strategy parameters for Dependent objetcs'
The system only performs scheduling or rescheduling if the constraints, such as relationships to be observed between the operations or orders are not violated as a result.
Thanks & Regards
Abhijit S Nakhwa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
please check the lot size and the resource capacity and also it might be due to master data issue so please run planning area consistency check and OM17
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.