on 08-04-2008 11:24 AM
Hi All,
Please suggest how can we assign budget profile to already existing project .
Hi Vishal,
You can go the Project builder, open the particular project and in the detail screen of the project definition, enter the budget profile in the control data tab page.
Or goto SPRO->Project system->Costs->Budget->Stipulate default budget profile for Project definition and assing the bedget profile.
Or enter the Budget profile in the Controlling tab page of the Project profile.
You can do all these for existing projects.
regards
Pratap.V