budget profile error

Former Member
0 Kudos

While creating budget through CJ30 for a project , the following Error message comes

"Assign plan/ budget profile to the object"

Although in the config. Budget profile is already assigned to that Project profile.

But through CJ02 ,in the control screen, the Budget profile field shows Blank for that project.

Please suggest solution as soon as possible.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Assign Budget to profile in your project manually and continue. It will work.

regards

Pratap.V

Answers (1)

Answers (1)

Former Member
0 Kudos

HI

Enter the budget profile in the T-code Cj20n or Cj02 mannually save it & continue.

It must be taken automaticaly when u select the Project profile, if it is not taken enter mannually & save it.

Regards

Raman T S