on 08-04-2008 7:54 AM
Hi Gurus,
Iam using PROMAN in PS module for Procrument,
When I enter in to the T-code CNMM (PROMAN)
I can see the PR generated automatically for the three materials under the Activity Network.
The materials are created in CJ20N (Project Builder).
I would like to know how these PR's are generated and how to raise the PR in PROMAN.
Thanks in advance,
Vasanth
Hi Vasanth,
I do not think that PR will get generated automatically.
Coming to the point of PR generation in proman, select a particular component in the right side of the screen. Then click the "execute" icon which the Blak and white flag at the right end of the screen. This will generate the PR.
regards
Pratap
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vasanth,
In Project builder (CJ20N), when the materials are attached to the activities, depending upon the status of the activity, a PR gets generated automatically. This PR is then converted to PO and further process goes on.
PRs can be generated also through ME51N.
In PROMAN, a particular project can be opened and the further processes of Goods movement are managed.
Hope I have understood your problem and put thigns clearly.
regards
Pratap.V
Hi Vasanth,
Basically PROMAN is a one-screen solution to handle all procurement related details, materials as well as services. One look at the PROMAN screen will give you clear picture about its usage. You have access to various documents generated for procurement, get stock details, access documents relevant to the materials, etc.
regards
Pratap.V
Hi Pratap,
As you said....
In Project builder (CJ20N), when the materials are attached to the activities, depending upon the status of the activity, a PR gets generated automatically. This PR is then converted to PO and further process goes on.
K....this happens when the Activity is released and process goes on....
my question is how the PR is generated automatically for the first time and once the PR to MIRO is completed...how to generate next PR for the same Materias linked to the Activity..
Thanks
Vasanth
Hi,
You can change the quantity in the material that you have attached in Project builder. This will renew the PR's quantity to the new value. Then follow the usual process.
eg:
Initial PR qty: 25 nos
PO qty: 25 nos
GR qty: 25 nos
GI qty: 25 nos
Assume that 25 more nos are required. Then change the qty in the material component to 50 nos. The PR changes as follows:
New PR qty: 50 nos
New PO qty: 25 nos (as already 25 nos are delivered)
New GR qty: 25 nos
New GI qty: 25 nos
Try out this. This will work.
regards
Pratap
Hi Pratap,
I have tryed out as you guided, it throws warning msg as the activity is released and PO is raised for the concern PR...but some how changed the Qty in component overview and raised the PO,MIGO n MIRO.....but is it the right procedure...i dont think so, coz we are using the same PR and changing the Qty...Is it the correct way...
So is it not possible to create PR for the 2nd time and further in PS/PROMAN
Thanks'
Vasanth
Hi Kish,
Hi Pratap,
I have changed the Qty, it throws warning msg as the activity is released and PO is raised for the concern PR...but some how changed the Qty in component overview and raised the PO,MIGO n MIRO.....but is it the right procedure...i dont think so, coz we are using the same PR and changing the Qty...Is it the correct way...
So is it not possible to create PR for the 2nd time and further in PS/PROMAN
Thanks'
Vasanth
Hi vasanth,
Nothing wrong with this procedure. But anyway you have the other option of attaching a material once again. The only issue with the former suggestin is that, we are playing with the already released/approved PR. so anymore changes will not require any firther PR approvals. Considernig this point, you can attach the material once again and continue.
regards
Pratap.V
Hi Vasanth,
As per my understand you want to create Multiple PR & then link those PR to your project.
Senario 1)
I will create a general PR with Account assignment category as P or N & link with nework & activity.
Now i need more materail for the same project & want to link to the same network & activity.
what i will do is go to ME52N change PR add Line item & link to the same.
Senario 2)
Before creating a Project i need to creat a PR & later on i want to assign that PR to Project.
Now for this senario create a general PR with Account assignment category as U & save the PR, after creating Project go to change & link in the same way.
The rest process remains the same PO, GR & IR.
Let me know if this suffies.
Regards'
Syed -
Edited by: Syed on Aug 6, 2008 9:26 AM