Dear Experts,

Can Any one tell me is there any Process...or Tcode to copy of costplan from one project to another project....

For EX....

X-Project...is having costplan(100)

Y-Project...?

Regards

Chandra

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear sai

u can copy the cost plan at the time creation, that to by copying the project in case of easycost planning.

Ex: u have created a project "X" completed the cost planning using easycost planning. creating a new project "Y", by using copy project "X". then u can copy the cost plan also.

Regards

Murali

Former Member
0 Kudos

Dear Murali Sir,

Thanx for valuable reply,i have rewarded points ,im closing the thread also.

Rgds&Thanks

Chandrasai