Hi friends,
Our client wants to handle the procurement of assets like computers, tables, chairs etc.. I feel this can be handled thru projects. But is there any advantage if I handle it thru PS?
Normally how is this procurement handled?
This is a bit urgent. Please help.
regards
Pratap.V
Dear vishnu
Let me illustrate, there two types of scenarios
1) procurement of material, which needs to be capitalized. - Normally In this case(which are direct procurement type, ex: purchase of computer, chair, etc.), no need to use PS module. Its unneccarily complicating the process .
2) procurement of material or services/material with long lead times (generally more than 6 months) with part deliveries, part payments, etc which needs to be capitalized.(ex: construction of new plant, office building) - PS module functionalites are very helpful.
Regards
Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pratap,
Yes you can handle this through PS.
You need to define you project.
1) Customer Project or Investment Project.
Create Hirerachy as required, & Map details process of your client.
Creat Materails & add in Project via CJ20N.
Regards'
Syed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.