hi all,

how can i use the condition type EK01 or EK02 in variant configuration. (i want to see calculated cost for config. materials in sales order)

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

hi ,

Ek01 : this is condition type used to get the actual cost from the material master and post in the sales order.

Ek02: this condition type used to get the calculated cost based on the master master which are selected at the time of the sales order.

example if i have material cpu = cost 10,000 in material master. Monitor = 5 000 , keyboard = 300.

if the monitor 15 inches : 5000 , 17 inches = 7000.

so the if we select variants CPU + Monitor 15 " + keyboard 15,300.

If we select variants CPU + Monitor 17 " + keyboard = 17,300. - Calculated cost.

so at to profit is calcualted based on EK02.

thanks

Kuntla

Former Member
0 Kudos

thanks a lot for your help.

can you tell me the customizing steps? Which customizings do i have to do to see this cost on the sales order? (step by step please)

Former Member
0 Kudos

Hi

Maintain the Condition type EK02 in ur pricing procedure

and

Maintain the condition records in vk11 for condition type EK02

maintain records for materials CPU, Monitor, and Keyboard

then when ur creating sales order , u can see at item level condition tabpage

Former Member
0 Kudos

if u want to maintain condition records for configurable materail

maintain codition records for condition type VA00 in vk11