on 08-02-2008 3:02 PM
Hi,
I have a finished product and 50 BOM components.Run a planning run with Heuristics sap_pp_020 in step-1and sap_mrp_001 in step-2.In DS-board i sorted the Planned orders of products by Low-Level codes.But It is not sequencing as per Low-Level code in the Board.What could be the reason?
Thanks&Regards
Venkadesh
Hello Venkadsh,
Have u executed levelling/sequencing function in APO. MRP _001 heuristic will plan assuming infinite sequencing.
Please try with with heuristic MRP _ 002 & check the results
if it does not work as per yr requirement, please try sheduling heuristic..
thanks,
Mangesh A. Kulkarni
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I assume you mean by using the Low Level Code as the scheduling sequence in the DS profile?
Ken Snyder
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi All,
This functionality is working after including the low-level code field in the DS Profile at customizing.
Thanks&Regards
venkadesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.