Overlapping between operations in PPDS

Former Member
0 Kudos

Hi,

I have one finished product and it has 2 semifinished products as components.If we run PPDS.Now my finished product 1st operation starts after completion of 2nd semi-finished product.But my requirement is finished product should not wait till arrive all its components.Finished product also starts its planning along with its components with some overlap in time.How to acheive this in PPDS?What setting to be done to acheive this?

Thanks&Regards

Venkadesh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

try to use an offset in the ppm of the FERT to overlap with your semifinished components...in the FERT ppm select your components and enter an offset.

Answers (0)