on 08-01-2008 1:09 PM
Hi friends,
In the project builder, I have the option of attaching documents to the material components and then a PR is generated. Can this document be viewed by the person who is converting this PR to PO? Because I want this document to be viewed by the vendor alongwith the PO released to him.
regards
Pratap.V
Hi,
In CJ20N, click on activity where materials are assigned and click on material overview button. Here select the material you wish to attach document adn clcik assign document butoon at the bottom.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
dear vishnu
if ur requirement is to make the document attached to the material availbel at various logistical processing levels, try to attach it to the material master level. This might solve your problem.
regards
Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear vishnu
Standard SAP provides with a solution for this requirement using PS texts. u can create PS texts specific to the material component and u can transfer to the PR. the following are the steps
1) In the network call up the component overview for a network or activity.
2) Select the components whose PS text you want copy into the purchase requisition.
3) Choose Components -> Copy PS text.
Hope this will solve ur problem.
Regards
Murali
Hi friends,
Please help me in the above doubt.
regards
Pratap.V
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.