on 08-01-2008 7:39 AM
Greetings,
Is there any reports for getting the production hours of a workcenter on a particular date?I would like to get the
schedule summary.The output must contain date and hours.
Helpful answers will be rewarded.
Regards,
Hi,
Did you get it or not?
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
MCP1 : Operation Analysis Selection
MCP7 : Work Center Analysis Selection
MCPB : Operation analysis: Dates
MCPH :Work center analysis: Dates
MCPK :Operation analysis: Quantities
MCPQ :Work center analysis: Quantities.
Hope will work for you. Reward if useful
Regards,
R,Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jinesh,
You can use MC10 - Flexible analysis for your requirement.
For this you have to create/change your own Evaluation using MC11/MC12 transaction.
Reward points if helpful
Regards,
Arpit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jignesh,
Run the trx "MCPH - Work Center Analysis: Dates ". It may help you.
Regards,
Shyamal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.