Hi,

Is there a program or a report that we could use to fix or unfix SNP orders. RRP4 is for PPDS orders and doesnt work for SNP orders.

We have a manual planning process that involves fixing and unfixing of orders is different horizons, and any help will be appreciated.

Regards,

Zeeshan.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello Zeeshan,

We had an issue right now, that whenever SNP Planned Orders are created, it is created as fix SNP planned orders. as you mention that you have horizon does the unfixing of plan orders, How do you set up such horizons?

Thanks.

Dgee

Former Member
0 Kudos

Hi,

Only available option in SNP as far as I know is ...use of CTM for fixing the order.But one cannot directly convert SNP planned orders to fixed status.You can copy it to other key figure and then this other key figure can be used as input demand for CTM. Run CTM with option in Planing Startegy as " Fixed Pegging" and CTM should create same planned and fixed orders.

rgds