Hi Friends,

I have created a project. I have assigned material to wbs, with cost element as cosumption a/c 40401100 ( GBB- VBR) and item as stock item. now after saving the project , PR generated with account assignment as 'Q' with g/l account 22401100( stock a/c BSX T/E key). So committment costs are not updating. If i create PR with account assignment as 'N' , then system will pick g/l acc as 40401100( consumption a/c) and committment costs are updating. I have checked costelement category for BSX 22401100, and found 90, balance sheet account. So please guide me how to fetch commiittment costs or how tofetch this stock account 22401100 at GR55 transaction...please reply.....

Edited by: k prasanna on Aug 1, 2008 5:08 AM

Edited by: k prasanna on Aug 1, 2008 12:56 PM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi

check you commitment item category.