on 07-31-2008 1:37 PM
Dear All
I would like my deliveries to consume the forecast in SNP , how should i map this scenario.
thanks in advance
Rajan
In SPRO --> check the requirement strategy setting (under APO --> Master Data > Product> specify requirement strategy).
Kindly note that requirement strategy like 10 or 20 map onto category group like K10.
You can check this category group under APO> SCP> Basis settings. It will have BM order category within this category group. You may want to include BR (delivery ) as well.
So a good thing would be not to mess up with existing requirement strategy but rather build up a new one that points to a category group that has BR in it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
make sure the requirement strategy is set appropritey (for eg 20}
the forecast consmption happens by matching some the forecast order type to the salesorders or deliveries
You specify whether the system checks against planned independent requirements in the future or in the past by setting the Consumption Mode field on the Demand tab page of the location-specific product master.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.