Hi All,
Customer's requirement is to plan cost on cost element level (in CJR2 or CJ40) on overall basis. They donot want to plan it on period basis. They want to check variance for a project overall but on cost element basis.
If I check Total Values in planning profile I donot get Cost elements.
Can somebody suggest please if this is possible without development.
thanks you.
regards
maneesh
Dear maneesh
Easy cost planning is the best method which suits ur requirement.
Regards
Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In your case, you can do either Unit costing/Easy cost planning as both are cost element based.
Unit costing is useful, where in you can enter the qty of materials (internal, external).
Easy cost planning is used for preliminary planning.It is possible only in CJ20N
In both the cases, you should have profiles.
Regards
N.Raju
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In your case, you can do either Unit costing/Easy cost planning as both are cost element based.
Unit costing is useful, where in you can enter the qty of materials (internal, external).
Easy cost planning is used for preliminary planning.It is possible only in CJ20N
In both the cases, you should have profiles.
Regards
N.Raju
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.