Hi experts,
I've faced a great probl. I published a BID Invitation as Contract with target value 100.000 for 10 unit for examples.
The vendor said that a BID Quotation is 15000 for unit, thus my contract will be 150.000.
Before a I acept the BID the contract total value is 100.000, not 150.000.
I need change the value because the workflow for approval is based in this value.
but I couldn't find the moment to change this value.
I hope you understand.
Thansk.
Paulo Afonso.
ok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can change the value in the quotation/Contract using the BADI "BBP_DOC_CHANGE_BADI".
BR,
Disha.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Disha,
I'm already using BBP_DOC_CHANGE_BADI with object BUS2121, when I active the filtter with BUS2200 and BUS2202 I lost the some data like ORG_DATA when I create a Bid Invitation.
I found that this badi use the lost data in the method BBP_BID_CHANGE even with no code inside. I have just code BBP_SC_CHANGE with checking object type (BUS2121).
How can solve this probl?: