cancel
Showing results for 
Search instead for 
Did you mean: 

Drive Project Structure

Former Member
0 Kudos

Hi all,

Ain't no way to make any changes in the hierarchy of the project after budjeting it ??

the system always gives this msg.

"A budget was already assigned for the WBS element A-01-01-01-001-002-002. You can no longer change the project hierarchy."

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Possible.

1. Delete the budget values on the WBS element.

2. Use T Code OPSX to reset the BUDG status on WBS.

Now you can make changes.

Regards

Sreenivas