hi,dear all:

I want to know how to specify the field status of "plant" of standard activity from "ready for input" to "required entry".

Can the field of the stand network be changed?

Thanks.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member203098
Active Contributor
0 Kudos

Hi,

Try in T-code OPN6

Regards,

0 Kudos

I change the "plant" with opn8,but it did not work,in opn6,I did not find "plant"