on 07-28-2008 6:04 PM
I am working with a consumption group but the forecast is not released from DP to SNP.
I followed documentation and I already configured the consumption group in customizing and assigned the consumption group in the product master.
In the release transaction I enter the product characteristic 9AMATNR, location characteristic APO_PLANT (which is a customized location characteristic). In the Consumption Group field I enter another customized characteristic (ZPROCID) and select an specific value for this characteristic in the "Orders with specific chars" button.
But when I execute the release I have a message saying "Release: Forecast" although it does not show any characteristic combination.
When I look at SNP I see that no forecast is transfered.
Please, can anybody help with this issue? I checked in the SAP notes but did not find any related issue.
Thanks,
Ric
in planning area setup have you mapped the location APO_PLANT as a location characteristic??
in the release transaciton have you used consumption strategy?
are you able to release without the consumption group setup?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ricardo,
pls let me know which requirement strategy you have choosen?
Regards
Sujay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ricardo,
Did you check the results log icon so that it tells you what it did? Also check these:
1. The material and plant you are releasing are CIFed from R/3 or maintained manually in APO.
2. Check whether you assigned product and location characteristics as 9AMATNR and APO_PLANT in Planning object structure>Extras> Assign product/location
3. When you release the forecast, you are releasing it to live cache. So, go to product view (/SAPAPO/RRP3) in APO and see if there is a forecast there.
If yes, then you didnot assign the ATP category to your key figure in SNP planning area.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Besides the configuration for plant / location in POS, I also updated the consumption group configuration to include Plant and Location characteristics. Previosuly I only had the ZPROCID characteristic in consumption group.
As additional information for other people, other important preparations:
Requirement strategy is 20 in APO.
Configuration for ATP has been copied with an integration model from ECC.