GR processing time

Former Member
0 Kudos

Hi,

What are all the places in APO where we can define GR/GI processing times?

1. product master

2. Transportation lane/external procurement relationships

Are there any other places where we can assign the value at? By the way, material is external procurement.

Accepted Solutions (1)

Accepted Solutions (1)

srinivas_krishnamoorthy
Active Contributor
0 Kudos

Location Product master and T Lane are the only two places I know of where GR/GI times exist. They are logical as well in context of external procurement. Having said that, there are flags in the system to consider/not consider GR time.

There are places though where you can set global GR times (eg. table /SAPAPO/SNPPARAM for SNP Global settings) There are some other applications in Forecasting and Replenishment module.