on 07-28-2008 6:10 PM
Hi,
What are all the places in APO where we can define GR/GI processing times?
1. product master
2. Transportation lane/external procurement relationships
Are there any other places where we can assign the value at? By the way, material is external procurement.
Location Product master and T Lane are the only two places I know of where GR/GI times exist. They are logical as well in context of external procurement. Having said that, there are flags in the system to consider/not consider GR time.
There are places though where you can set global GR times (eg. table /SAPAPO/SNPPARAM for SNP Global settings) There are some other applications in Forecasting and Replenishment module.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.