on 07-28-2008 9:24 AM
Dear experts,
Need some help in Budget carry forward of IM & PS.
My scenarios is I have a Investment program in the year 2008 and under that program i have 1 project, which is having a duration of 3 yrs.
After completion of 1st yr i.e., 2008, i need to carry forward the remaining budget to the next year i.e., 2009.
But here I am getting a problem.
Please go through the below steps i followed:
1st in Investment Management:
1. Tcode IM 27: here I am carrying out this transaction with the existing Investment program and approval year, system automatically prompting the next approval year in Target investment program.
In settings I selected 1st 3 options.
Copy program structure
Carry forward meas / app req
Carry forward budget values
If select the 4th option i.e., carry forward planned values system is asking for version, which i have not maintained for the Investment program.
then executed the transaction
system giving messages investment program copied to xxxx/2009
budget values were carried forward from xxxx/2008 to xxxx/2009
measures / approp req. were copied from xxxx/2008 to xxxx/2009.
2. In T Code IM27_close.
Investment program: xxxx
Approval year: 2008
in settings selected the following:
Carry forward meas / appr. req
Carry forward budget values
in selection of measures / approp reqs for transfer to current approval year selected:
All meas / appr req.
then executed the transaction
systems gives the output
Budget values were carried forward from xxxx/2008 to xxxx/2009
Measures/approp. requests were copied from xxxx/2008 to xxxx/2009
3. in T code IMCAOV
Investment program xxxx
Approval year 2009
sender fiscal year 2008
ticked
Test run
Budget as supplement / return
executed
output is
The program was executed in test mode
Data can be updated
Again run the same transaction without Test Run
the output is
The program was executed in update mode
Data was updated successfully.
Now I run the T code IM32 to check the budget with new approval year
Investment program xxxx
approval year 2009
here system took the distributed values of the last year investment program, i.e.., xxxx/2008.
My doubt is the budget for the new year 2009 should be the Distributable value of old year 2008, why system is picking up the distributed value of old year 2008 to new year 2009?
Please clarify me the above..
Thanks in advance.
Best regards,
Dear Ecperts,
Can anyone please help me out in this regard?? Its bit urgent? Am I following the right process?
Please help me out.
Thanks and Regads,
Raju.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.