on 07-27-2008 9:01 AM
Hi All,
When i am doing PGI with Movement type 281 Q and after checking my reports ,the actual costs are showing against the WBSE not against the Network Activity.
Please advice me is there any setting to do this so that after doing PGI i will should get the costs against the Network Activity.
Regards
Firdosi
closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check the profile of Parameter for network,(OPUV) . There u must have missed to tick Activity account assign.
Regards
N.Raju