Remaining Order Plan

Former Member
0 Kudos

Dear Experts,

In Report S_ALR_87013558 The term "Remaining Order Plan" is coming. This is reducing the budget available.

Do you know the solution to overcome this problem?

SSanjay

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Apply tecnical close status, with this you indicate that you have finished the operation and will cancel the comitments...

Former Member
0 Kudos

Thanks Dear,

But my project/order is not completed, so I don't want to mark it as TECO.

Any other solution?

SSanjay

Former Member
0 Kudos

Dear Experts,

Help required

I got that remainig order is Maximum of Plan & Actual order values at WBS level.

But Budget does not allow me to create new PO.

It is counting Remaining Order plan value also.

How do we proceed with Rem Ord Values?

SSanjay