How to allocate budget for plant maintenance.

madhan

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Budget: Amount of resources allocated under a particular head in a financial year.

Budget Control: Having/ creating a control on the resources allocated in a financial year.

Original Budget: The initial budget that you have allocated to a WBS element.

Supplement of Budget: One time/ discrete increment in the original budget.

Return of Budget: Taking out the unutilized portion of the budget.

Transfer of Budget: Transferring the budget among two or more expense heads.

Project Definition: A framework for a business undertaking with a fixed goal to achieve with given resources.

The project definition contains dates and organizational information that are binding for the entire project.

WBS Element: Individual structural element in a work breakdown structure (WBS) representing the hierarchical organization of an R/3 project. Describes either a concrete task or a partial one that can be further subdivided.

Proposed Business Process

Assume there are seven expense heads in maintenance department. There may be addition of expense head in near future.

Based on the maintenance heads, maintenance department will create a project in project system. This project will be used for ‘statistical purpose’ only & will not have any financial implication.

Upon creation of a project, WBS elements will be created as per the expense heads. So for each expense head, there will be one top level WBS element. Again these WBS elements will be divided in twelve WBS elements. These twelve WBS elements represent twelve calendar months.

Budget will be allocated to each WBS element & the WBS element will be released from the project.

Maintenance department will create maintenance orders as per their work requirements. These orders will be settled to cost centre, which is maintained in the settlement rule. Also WBS element will have to be mentioned in each order so that the budget control can take place. So as to capture cost from each maintenance order, the WBS element field will be made ‘mandatory field’ in maintenance order.

So when a maintenance order is released, system will do a budget check against the WBS element mentioned. If the budget check status is OK, order is released or else it will stopped from release. If the order is stopped from release, maintenance department will have to supplement the budget. Upon supplementing, the order is released again & the maintenance cost such as, labour, material costs can be booked on the order. Again the order cost is settled to cost centre & at the same time, budget is consumed from the respective WBS element.

Every year, maintenance department will copy the previous year’s project so as to save time & efforts to create project & WBS elements. And the maintenance department will assign the budget allocated to each WBS element in a financial year.

It is also possible to return the unutilised budget or, transfer of budget from one WBS element to another.

Create a project CJ20N

Create WBS element CJ20N

Assign Budget to WBS elementsKO22

Display assigned Budget KO23

Supplement Budget KO24

Display Supplement budget KO25

Return Budget KO26

Display Return budget KO27

Transfer of budget CJ34

Hope u wull get ur answer if yes reward with points

Regards,

R.Brahmankar

Answers (2)

Answers (2)

former_member187991
Active Contributor
0 Kudos

hi

first consult with CO and create budget profile ,assign this budget profile to you order type in IMG , then you can specify the budget in T code KO22

regards

thyagarajan

Former Member
0 Kudos

Hi Madhan,

Refer the link

[Budget Planning for Plant Maintenance and Customer Service |http://help.sap.com/saphelp_nw04/helpdata/en/d2/9e71403017587ee10000000a155106/frameset.htm]

Regards,

Shyamal