on 07-25-2008 10:04 AM
Dear All,
We are trying to create plan order with help of PPDS PDS. But i am not able to create Pl Orders with PDS which have multiple setups.
it gives error for locked activity network, but if i use ppm insted it creats the order.
Any input would be helpfull
also i am integrating SAP R/3 4.7 to SAP SCM 2007
Regards
Negi
Hello Arun,
How u have generated PDS in APO? Is it based on R/3 BOM, routing ?
If yes, please check " Plan explosion" in configuration (SPRO - PPDS- GLOBAL SETTINGS -MAINTAIN GLOBAL PARAMETES & DEFAULTS) & Material Master (PPDS View)
If it doesnot solve the proble, proive the error no with detailed information
Thanks
Mangesh A. Kulkarni
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Mangesh,
I have already maintained all the above settings, also PDS was created from R/3.
Error I get is: different setup keys for activity with lock activity chain
This happens only for PDS which have multiple setup phase with same setup group
I am able to create planned order with PPM but not with PDS.
Thank you
Regards
Negi