I got one Process order stoped in my CIF Inbound queue with the error "PI dummy activities cannot have input\output nodes". Somebody know how to indentify the problem and how to fix ?
Thanks a Lot.
Daniel Campos
Hi,
Please check your BOM and process order,I belive there should be some discrepency you might be added some quatity in process order at the operation level actually that should be added at phase level not in operation level,remove the additional quatity from operation and add it at phase level then this error will not come.
I hope this will help,do let me know if its working.