on 07-24-2008 2:31 PM
Scenario -
I create a Breakdown Maintenance Order. Stock item - Material assigned to the Order. No Stock in Stores. We get a new material from near by company. Material enters with reference to their returnable gate pass. Material comes to our stock. Material replaced.
We purchase the same material and give it to them.
Dear,
If it is from other company then it is a procurement activity comes under MM , You need to creat PO (Purchase Order Cycle) & if you are sending them then SO (Sales Order cycle)
Ramesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Scenario -
I create a Breakdown Maintenance Order. Stock item - Material assigned to the Order. No Stock in Stores. We get a new material from near by company. Material enters with reference to their returnable gate pass. Material comes to our stock. Material replaced.
We purchase the same material and give it to them.
How we will map in SAP.
Have you all understood my question.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.