problem in rvenue genration

Former Member
0 Kudos

Dear all

When i try to do sales order (VA01) again my WBS which i have attach milestone & billing plan allready but in sale order i cant see WBS element field in assignment tab. pl gave solution on this urgently.due to this actual revenue not generate pl gave solution

Regards

Prathamesh

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

HI,

1.in opo8 mark intergrated planning indicator for your project profile.

2.Mark the WBS where you want to plan revenues or post revenues as billing element.

3.In planning profile , under automatic revenue planning mark from sales order check box ,if u want revenue to be planned in WBS from sales order or mention REelem billing plan if you want plan revenues in WBS from Billing plan maintained in sales order.. check the settings nd revert back.

regrds

pushpa