on 07-23-2008 1:23 PM
Hi,
Experts
Can any one explain the flow for Customer supplied material
for processing labour charges only.
How can i start the inward material, and return it with billing.
Thanks & Regards
Yogesh
Dear Yogesh
- Create the material (say M1) in receiving plant with material type UNBW.
- While doing MIGO, only stock quantity getting inwarded without any values
- Create M1A as HALB
- Create a BOM in CS01 for M1, keeping M1 material as the header component and M1A as component
- Confirm the service by one operation with material code M1A (material type HALB) through MFBF
- While doing PGI, stock at servicing plant will get reduced.
- HALB being sent to Customer with no ED, Cess, Tax etc.
- Raise an invoice (charging ONLY for service charges)
- TDS applicable
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.