IDOC XI - Scenario

Former Member
0 Kudos

Hi

Please find our requirement below.

SAP ECC ---> SAP XI 7.0 ---> Third party application.

In the above landscape we have our configurations, connections intact and everything is working fine.

When we create a material/vendor etc, in ECC automatically an IDOC should get created there and this should get transferred to XI and then update in third party applications database.

I have already configured IR and IB with central SLD in XI and RFC connections, logical systems, Port definitions etc...but IDOC is not getting created automatically when a material is created and saved.

Please let me know what are the steps I need to follow for this automatic IDOC creation and transfer it to XI and process it there?

Any help would be greatly appreciated.

-Subbu

Accepted Solutions (1)

Accepted Solutions (1)

MichalKrawczyk
Active Contributor
0 Kudos

hi,

you need to activate change pointes in R3 system for matmas messages

http://help.sap.com/saphelp_erp2005vp/helpdata/en/12/83e03c19758e71e10000000a114084/content.htm

and schedule report RBDMIDOC which will generate IDOCs from those change pointes

this is the only way to send them "automatically" in standard

Regards,

michal

Answers (0)