on 07-22-2008 3:25 PM
Hi all
I am configuring a PR release strategy taking 3 characteristics and release procedure is as per the classification:
Characteristics i have taken are :
1. Document Type(ceban-bsart)
2. Plant (ceban-werks)
3. PR total value (ceban-gswrt)
I have done all the Release strategy configuration
as
release group r1 strategy s1
release group r2 strategy s2
release group r3 strategy s3 as per the value in the PR
but when i run the pr and view the strategy it is only picking only the one release strategy s1 with release group r1 whatever the value may be !!!!!!!!!
Next is when i check the Overall release strategy tab in release group defining then PR is not picking any release strategy.
Please help me out.
Its Very Urgent
Closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In release strategy, under classification, did you defined the proper values (e.g. <=, etc) for field CEBAN-GSWRT? Please ask your question on Material Management forum.
http://www.sap123.com/showthread.php?t=59
BR
Csaba
Edited by: Csaba Szommer on Jul 22, 2008 6:00 PM
Edited by: Csaba Szommer on Jul 22, 2008 6:01 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes Dear
I Have defined the values like
< 1000.00 INR
1000.00 - < 100000.00 INR
> 100000.00 INR
each value fro a separate release strategy s1,s2,s3 respectively,,,
also i have seen the link you have referred,,,,
But still i am unable to get the strategy
I have also posted under MM forum
please help me out
points will be rewarded for the same
Regards