Purchase requiistion release strategy

Former Member
0 Kudos

Hi all

I am configuring a PR release strategy taking 3 characteristics and release procedure is as per the classification:

Characteristics i have taken are :

1. Document Type(ceban-bsart)

2. Plant (ceban-werks)

3. PR total value (ceban-gswrt)

I have done all the Release strategy configuration

as

release group r1 strategy s1

release group r2 strategy s2

release group r3 strategy s3 as per the value in the PR

but when i run the pr and view the strategy it is only picking only the one release strategy s1 with release group r1 whatever the value may be !!!!!!!!!

Next is when i check the Overall release strategy tab in release group defining then PR is not picking any release strategy.

Please help me out.

Its Very Urgent

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Closed

csaba_szommer
Active Contributor
0 Kudos

Hi,

In release strategy, under classification, did you defined the proper values (e.g. <=, etc) for field CEBAN-GSWRT? Please ask your question on Material Management forum.

http://www.sap123.com/showthread.php?t=59

BR

Csaba

Edited by: Csaba Szommer on Jul 22, 2008 6:00 PM

Edited by: Csaba Szommer on Jul 22, 2008 6:01 PM

Former Member
0 Kudos

Yes Dear

I Have defined the values like

< 1000.00 INR

1000.00 - < 100000.00 INR

> 100000.00 INR

each value fro a separate release strategy s1,s2,s3 respectively,,,

also i have seen the link you have referred,,,,

But still i am unable to get the strategy

I have also posted under MM forum

please help me out

points will be rewarded for the same

Regards