on 07-22-2008 12:32 PM
Dear SAP PS Experts,
Can any one explain step by step of network scheduling.
User has been created number of networks,in one project,now its all networks are released,is there any solution to me to make single network.
Thanks in Advance
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Network scheduling is the process of calculating the dates when the activities assigned to networks should be performed. If the user has created several network activities, it is still possible to schedule them and plan dates for project separately. If for some reason only one network should be used, then if network status allows that, you may still delete the networks that are not needed and create all activities under one network header.
You may read more on scheduling in sections PS -> Dates, under the following link
[http://help.sap.com/saphelp_erp60_sp/helpdata/en/c0/1885347860ea35e10000009b38f83b/frameset.htm]
Kind regads,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This is the wrong forum....
Anyhow did you read the PS guide... (this one is an old one)
http://help.sap.com/printdocu/core/Print46c/en/data/pdf/MYSAP/SR_PS.pdf
Regards
Juan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.