Project Stock is showing in Sales Order Stock

Former Member
0 Kudos

Hi Gurus,

While making Sales order, we are entering WBS element, after this system automatically creates Purchase requisition and then PO.

When we do GR, system shows stock in sales order stock in place of Project Stock.

We want system to show it in project stock.

Please revert asap

Thank you

Accepted Solutions (1)

Accepted Solutions (1)

ansar_shaikh2
Contributor
0 Kudos

Yes man, there is a way, have a look at Project Profile, OPSA, there are 4 tabs --

Control, Organization, Plg board/dates, Controlling.

In Control tab 3options are there in Project Stock.--

no stock -- non-valuated stk -- valuated stock - or automatic grouping.

check which settings you are having in your project profile which is assign to your project.

tick which ever you want to assign according to your needs.

hope this will help you.

Regards,

Ansar