cancel
Showing results for 
Search instead for 
Did you mean: 

CJ40 Manual Cost Planning

stheurkar
Active Contributor
0 Kudos

Dear All,

In my project scenario i have to use CJ40 Cost planning by using cost element.

For that i have to define cost element which will come in CJ40 Primary Cost screen.

Then i can plan the cost with ref. of cost element.

But i don't know where i have to define the cost element & where same to assigned with PS module.

Can any one pls give me step by step procedure for the defining cost element & assignment with PS module.So that cost element will be reflected in CJ40 Transction at Primary Cost screen.

Then i can do the cost planning of WBS

Pls give me a solution as early as possible.

Thanks in Advance.Points will be rewarded,

Regards,

Sandeep Theurkar

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

T Code OPSB (Planning Profile) assign the Cost element group for primary costs. Use this profile in the project profile and inturn on WBS element.

Take help of CO consultant in creating the CE group which is usually done using T Code KAH1.

You should be now seeing all the CE (grouped) in CJ40.

Regards

Sreenivas

stheurkar
Active Contributor
0 Kudos

Thanx Sree,

Problem solved.

points rewarded.

Regards,

Sandeep Theurkar

Answers (0)