Hello Gurus,

where can I set replenishment lead time?

Many thanks,

Frank

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Friend,

The RLT can be set in the Masters Materials.MMR and Also in the Documnet Type Configuration.

But as per SAP standard Procedure the Prority will be the document type.

That means the RLT given in the Order document will overseed the RLT given in the MMR.

regards,

SAP SD

Answers (3)

Answers (3)

Former Member
0 Kudos

Replenishment lead time for different for different material are different.

For, Trading goods,it is

Planned delivery time + Goods receipt processing time.

For, Finish product, it is

The in-house production time.

Former Member
0 Kudos

hi

In material master , MRP 3 area.

thanks

Kuntla

Former Member
0 Kudos

HI,

You can set up this in VOV8 document type funcitionliyt - Lead time days field as well as material master data MRP views also..

Regards