We are construction company, so we only purchase materials when have requirement from a project, in this case the price control of material is V or S?
Please give me your advice!
Thanks
Long
Hi,
In case of inhouse production price control 'S' is advised and in case of boughtout 'V'.
Search for threads in MM forum, you will get a lot of info.